What One Should Do In The Case Of Cost Overrun

Leadership Recently, your project exceeded its estimate and the customer insisted that you and your organization absorb the extra costs. Is this fair?

It depends on the way your contract was written, but probably the customer is correct. Common sense would dictate that if you want to keep your customer as a customer you would not go out of your way to make him or her unhappy by charging for overrun. However, eating the cost yourself for fear of being sued is like doing the right thing for the wrong reason. The best way to handle this is to handle it ahead of time -- through the contract. The contract should stipulate who pays in the event of exceeding costs laid out in the projection -- and if it looks like the projection is too low, there should be a request for a contract amendment if such a clause is not stipulated initially. Contracts are the best way to navigate tricky waters like these, because money can quickly become a thorn in relationships. Therefore it is essential to have the details hammered out ahead of time.

As Anderson (2015) points out, "if it's not written into the contract, without an 'approved' change request for more money, you as the provider are going to be stuck doing the extra work to get the 'promised' job done, with no...

Likewise, Schwartz (2015) notes that when negotiating contracts, it is important to be aware of the rights that each party wants to hold onto. A business relationship is not one-sided and both parties want to benefit from the relationship -- thus, risk (such as overrun) should be considered by both parties before work commences. This way there are no surprises down the road if that risk actually turns out to be a reality. The contract will have already prepared both parties for this possibility.
References

Anderson, C. (2015). Project Management. LinkedIn. Retrieved from https://www.linkedin.com/pulse/project-management-cost-overruns-pay-christopher-anderson-msit

Schwartz, B. (2015). The Legal Rights of Union Stewards. MA: Work Rights Press.

Topic 2: Professionalism (1 page) the reading is attached (please use reference to show your research)

According to Kwak and Anbari (2012) EVM adoption helps organizations to integrate "scope, schedule and resources" as well as to measure the performance/progress of the project. EVM is a helpful integration discipline because it provides the necessary framework and method…

Sources used in this document:
References

Kellermans, W., Floyd, F., Veiga, S., Matherne, C. (2013). Strategic alignment: A

missing link in the relationship between strategic consensus and organizational performance. Strategic Organization, 11(3): 304-328.

Kwak, Y., & Anbari, F. (2012). History, practices, and future of earned value management in government: Perspectives from NASA. Project Management Journal®, 43(1), 77-90.
Cite this Document:
Copy Bibliography Citation

Related Documents

Business Policy Case Study Analysis
Words: 2837 Length: 10 Document Type: Case Study

Those did not have much power on the manufacturer, however, the consumer were rather sophisticated, so maintaining the high quality standards was crucial. Substitutes. After the trade liberalization, Phillips had an enormous pressure from Asian companies that managed to copycat its products and the price performance of the substitute products was net superior. Supplier power. The suppliers did not have high bargaining power. The high tech industry in Europe and U.S.

Capital Budgeting Financial Analysis of a Mineral
Words: 758 Length: 3 Document Type: Essay

Capital Budgeting Financial Analysis of a Mineral Resources Opportunity on the North Ridge of Mt. Zircon Situation Overview Engineers working for Peru Resources have proposed a new mine on the North Ridge of Mt. Zircon. They have discovered a vein of transcendental zirconium ore that led them to believe that there was a sufficient amount to produce roughly 340 tons of this mineral per year for a seven-year period. Furthermore, it was believed

Analytics and the Growing Dominance of Big
Words: 2022 Length: 5 Document Type: Essay

Analytics and the Growing Dominance of Big Data are Revolutionizing Strategic Decision-Making The level of uncertainty and risk that pervade many enterprises today is growing, as the dynamics and economics of markets are changing rapidly. The many rapid, turbulent structural changes in industries is also leading to a greater reliance on analytics and the nascent area of Big Data as well. The potential of this second area, Big Data, is in

Project Financing International Project Finance:
Words: 5068 Length: 15 Document Type: Essay

This can subsequently result as the massive benefits to the commercial contestants devoid of the incurring of the extra cost that pertaining to such commercial participants. The participation of the export credit agencies accompanied by the existing multilateral developments institutions normally results to the lofty stage of the ecological, employment and other supplementary social standards, which are extremely expensive and cumbersome to, accomplished. The application these existing social standards are

EMR for Large Company
Words: 3022 Length: 11 Document Type: Essay

EMR There are several criteria by which the company can establish acceptability for the eCube system of EMR that is available from Fresenius. The first stakeholder group consists of the patients, who will benefit from the enhanced functionality that comes from the eCube system, in particular the superior health outcomes that come from having accurate medical histories available to physicians and other practitioners while they are working with the patient. Management

Today's IT Project Management
Words: 2403 Length: 9 Document Type: Research Paper

Project Management and the Federal Sustainable Energy Initiative Today's IT Project Management The Project Management Failings of the Obama Administration's Sustainable Energy Initiative Dr. Beverly JN Bowen, PhD As the global economy continues to suffer the devastating consequences of unchecked growth, in the form of a prolonged recession which has decimated the housing market, private enterprises and public policymakers alike have a vested interest achieving a sustainable form of urban development. Seeking a balance

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now