Verified Document

Earned Value Management Affect Profitability  Term Paper

This problem is compounded by the fact that these large projects are being carried out in multiple contractor organizations, each of which employs its own peculiar planning and control system (Frame, 2002). By the early 1960s, it became increasingly apparent that the Defense Department was no longer able to track the efforts of its contractors with accuracy. It decided that contractors on large, complex projects should be required to report their project efforts in a consistent fashion. It worked to develop rules for reporting project progress and in 1967 issued Department of Defense Instruction (DODI) 7000.2, known also as the Cost/Schedule Control System Criteria (C/SCSC). In 1972, the Defense Department issued its Joint Implementation Guide, which gave practical advice on how to implement DODI 7000.2.The focus of the earned value system was the development of consistency and management discipline in contractor organizations in five areas:

Organization. Instructions are provided on the development of work breakdown structures and organizational breakdown structures.

Planning. Key planning requirements are highlighted -- for example, the establishment of performance baselines.

Accounting. Requirements are specified for the collection and maintenance of cost accounting data.

Analysis. Guidance is offered on use of earned value techniques for reporting budget variance, schedule variance, and EAC.

Reporting. Instructions are given on reporting project status through cost performance reports (CPRs), which are required on very large projects, or cost and schedule status reports (C/SSRs), which are less burdensome to generate than CPRs and are required on smaller projects.

In the 1990s, the earned value approach as promulgated by the Defense Department underwent a number of modifications. In 1991, DODI 7000.2 was superseded by DODI 5000.2, which was in turn was superseded by DOD Regulation (DODR) 5000.2-R in 1996. The Joint Implementation Guide was revised and replaced by a document titled Earned Value Management Implementation Guide in 1997. The current version of the earned value management system is designed to be less bureaucratic than its predecessors. It focuses less on mandating certain actions and more on providing guidelines (Frame, 2002).

According to Straight, Lawler and Schwartz (2003), earned-value management is not a new concept; however, the newly revised Office of Management and Budget (OMB) Circular a-11, Preparation, Submission, and Execution of the Budget may represent the first opportunity many government managers have had to work with these techniques. In this regard, Frame (2002) advises that, "In the 1990s, the earned value approach as promulgated by the Defense Department underwent a number of modifications. In 1991, DODI 7000.2 was superseded by DODI 5000.2, which was in turn was superseded by DOD Regulation (DODR) 5000.2-R in 1996. The Joint Implementation Guide was revised and replaced by a document titled Earned Value Management Implementation Guide in 1997" (p. 290). The current version of the earned value management system that is in place was intended to be less bureaucratic than its predecessors and concentrates less on mandating certain actions and more on providing guidelines (Frame, p. 290).

Because of the big-project focus of the Defense Department's approach to earned value management, coupled with many managers' unfamiliarity with the process, organizations outside of the defense community were unaware of its potential usefulness on nondefense projects. This situation began to change in the late 1980s. The earned value approach can be used effectively on small projects when bureaucratic requirements -- such as those found in DODI 7000.2, DODI 5000.2, and DODR 5000.2-R -- are stripped away. Today, most project management leaders in high-performing organizations acknowledge the great contribution the earned value method can offer them in planning, executing, and controlling their projects (Frame, 2002).

For federal agencies, Circular a-11 requires the use of an earned-value approach them to monitor and manage their capital asset projects' information technology, buildings, structures, major rehabilitation, land, vehicles, furniture, and equipment. In addition, Circular a-11 requires agencies to submit, as part of their annual budgets, a capital asset plan and business case (see proforma Exhibit 300 at Appendix ____) for each capital asset project. Completing the exhibits requires calculating the earned value for each project (Straight et al.). In this regard, Circular a-11 states that, "Earned value management (EVM) is a project (investment) management tool effectively integrating the investment scope of work with schedule and cost elements for optimum investment planning and control. The qualities and operating characteristics of earned value management systems (EVMS) are described in American National Standards Institute (ANSI)/Electronic Industries Alliance (EIA) Standard -748-1998, Earned Value Management Systems, approved May 19, 1998. It was reaffirmed on August 28, 2002" (p. 579).

Table 1.

Performance Management Thresholds

Contract Total Estimated Value, Then-Year $ (Note 1)

EVM Implementation (Notes 2,3,4,5,6,7,8)

CPR

Data Item

Note...

Thresholds are in then-year dollars and refer to total estimated contract value including options.
Note 2. For procurements equal to or greater than $20M but less than $50M, the contractor must comply with the guidelines in ANSI/EIA-748, but a validated Earned Value Management System (EVMS) is not required.

Note 3. For procurements equal to or greater than $50M, the contractor must have a validated EVMS that complies with the guidelines in ANSI/EIA-748.

Note 4. Integrated Baseline Reviews (IBRs) are required whenever Earned Value Management (EVM) is required (contracts equal to or greater than $20M).

Note 5. The application of EVM is discouraged on Firm-Fixed Price (FFP) (including FFP with economic price adjustment) contracts, subcontracts, intra-government work agreements, and other agreements, regardless of dollar value. In cases where cost/schedule visibility is required, such as for development work equal to or greater than $20M, the program manager must obtain a waiver for individual contracts from the Milestone Decision Authority. The program manager will prepare a business case that includes rationale for why a cost reimbursable or fixed price incentive contract is not an appropriate contractual vehicle. Considerations for applying EVM in these situations may be found in the DoD Earned Value Management Implementation Guide (EVMIG).

Note 6. The application of EVM to work efforts that are not discrete in nature (non-schedule based), such as level of effort, time and materials, and services, should be considered on a case-by-case basis. In cases where the nature of the work does not lend itself to the meaningful use of EVM, it may be appropriate to waive the EVM requirement. When EVM is waived, the program manager will implement an alternate method of management control.

Note 7. The application of EVM on cost or incentive efforts less than $20M is optional and is a risk-based decision that is at the discretion of the program manager. A cost-benefit analysis should be used as a basis for the decision to implement EVM. Considerations for applying EVM in these situations may be found in the DoD EVMIG.

Note 8. The application of EVM is not required on contracts of less than 12 months in duration.

Note 9. A Contract Performance Report (CPR) (Data Item Description (DID) number DI-MGMT-81466A) and an Integrated Master Schedule (IMS) (DID number DI-MGMT-81650) are required whenever EVM is required (contracts equal to or greater than $20M).

Note 10. No specific application thresholds for Contract Funds Status Reports (CFSRs) are established; however, application to contracts of less than $1.5M in then-year dollars should be evaluated carefully to obtain only the minimum information required for management control. CFSRs should not be applied to FFP contracts or contracts of less than 6 months in duration.

Note 11. A product-oriented Work Breakdown Structure (WBS), in accordance with the DoD WBS Handbook (MIL-HDBK-881A) and the Contract Work Breakdown Structure (CWBS) DID (DID number DI-MGMT-81334C), is mandatory when EVM is implemented and a CPR and an IMS are required. For contracts that require Contractor Cost Data Reports (CCDRs), the CWBS will be developed, approved, and maintained in accordance with DoD 5000.04-M-1, Cost and Software Data Reporting Manual, and the CWBS DID (EVM contract requirements checklist, 2008).

The Electronic Industries Alliance (EIA) has issued a standard for EVMSs (EIA-748-a, January 2002), in accordance with the American National Standards Institute (ANSI). According to their organizational Web site, "The Electronic Industries Alliance (EIA) is a national trade organization that includes the full spectrum of U.S. manufacturers. The Alliance is a partnership of electronic and high-tech associations and companies whose mission is promoting the market development and competitiveness of the U.S. high-tech industry through domestic and international policy efforts. EIA, headquartered in Arlington, Va., comprises nearly 1,300 member companies whose products and services range from the smallest electronic components to the most complex systems used by defense, space and industry, including the full range of consumer electronic products" (EIA, 2008, p. 2).

The EIA standard identifies seven fundamental principles of an EVMS, applicable to all projects, regardless of size. (the EIA standard provides additional guidelines applicable…

Sources used in this document:
Bibliography

Dennis, C., & Harris, L. (2002). Marketing the e-business. London: Routledge.

Dinsmore, P.C. & Cabanis-Brewin, J. (2006). The AMA handbook of project management. New York: AMACOM.

Fleming, Q., & Koppelman, J. (2000). Earned value project management, 2nd ed.

Pennsylvania: Project Management Institute.
What is earned value management? Earned Value Management. [Online]. Available: http://www.earnedvaluemanagement.com/.
EIA. (2008). Electronic Industries Alliance. [Online]. Available: http://www.eia.org/new_about/index.phtml.
EVM contract requirement checklist. (2008, April 28). U.S. government. [Online]. Available: http://www.acq.osd.mil/pm/documents/EVM_Contract_Req_Checklist_apr08.doc.
What is earned value management? Earned Value Management. [Online]. Available: http://www.earnedvaluemanagement.com/.
Cite this Document:
Copy Bibliography Citation

Related Documents

Value-Based Management
Words: 2770 Length: 10 Document Type: Term Paper

Value-Based Management (VBM) is a management philosophy that aims to achieve superior results (Niedell, 1996). This process measures performance by the value that is returned to shareholders. Successful implementation of VBM requires a successful change in corporate culture, as well as the adoption of VBM concepts at all levels and functions within an organization. VBM includes an integration of performance measurement, compensation, strategic planning, training, and communication (Porter, 1986). The

Supply Chain Management Hypothesis Defined Concepts of
Words: 24788 Length: 80 Document Type: Thesis

Supply Chain Management Hypothesis defined Concepts of SCM and the evolution to its present day form Critical factors that affect SCM Trust Information sharing and Knowledge management Culture and Belief -- impact on SCM Global environment and Supply Chain management "Social" and "soft" parameter required for SCM Uncertainties This chapter aims to give an outline and scope of the study that will be undertaken in this work. The study lays out the issues faced by manufacturing organizations when it comes

Time Management in Organizations: A Review of
Words: 1358 Length: 5 Document Type: Dissertation

Time Management in Organizations: A Review of Literature Time management as a process and research construct have numerous dimensions that makes it dynamic and, from the researcher's perspective, susceptible to being measured incorrectly when tested for cause-and-effect study types. In this review of related literature on time management, focus would be on how this process and construct is implemented at the organizational level. Application of time management in organizations would be

Shareholder and Stakeholder Values It
Words: 8113 Length: 30 Document Type: Term Paper

In other respects, however, the evidence does not readily conform to theoretical predictions. For example, if gross job turnover is taken as a rough proxy for labor market flexibility -- and since stringent EPL reduces both hiring and firing -- it is quite surprising to find that job turnover rates are very loosely related to EPL rankings. Most remarkably, not only are the estimates for Italy and France, at

Value Chain Analysis Examine Factors Behind Any Changes in the Structure...
Words: 2443 Length: 9 Document Type: Essay

Value Chain of Marathon Oil When considering the ever-changing and highly competitive global landscape of business today, firms must stay at the cutting edge of their respective fields in order to sustain profitability in the long-term. Accordingly, companies are faced with the continuous task of finding new ways to understand and subsequently accommodate market demands, while simultaneously securing lucrative business models and job environments. The Marathon Oil Corporation and its

Value of Accounting Standards
Words: 3077 Length: 9 Document Type: Term Paper

Value of Accounting Standards Accounting rules are designed to serve the capital markets and make these markets work efficiently. Accounting rules are essential to the efficient functioning of the economy because decisions about the allocation of resources rely heavily on credible, concise, transparent and understandable financial information. Without standard measures of the worth of a company, lenders and investors would have no way in which to evaluate the worth of

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now