Construction Daily Field Construction Report

DeMatteis/Turner Construction Site

Contractor:

DeMatteis/Turner

Report No:

Weather

Temperature Conditions a.MP.M

Low Temperature: |_| Partly Cloudy . |_|

High Temperature: 50F |_| Cloudy |_|

|_| Windy |_|

Notes ? |X| Rain |X|

|_| Snow |_|

|_| Other ? |_|

Workmen/Visitors

Total Total Total

Abatement ? Field Staff ? Plasterers 1 Others: (list trade)

Balancing ? Finish Carpenters 1 Plumbers ? 1 safety officer ?

Carpenters 7 Flooring ? Roofers 1 laborer

Caulking ? Insulator ? Sheet metal

Ceiling Iron Workers ? Sheet rockers/Tapers

Concrete Finishers ? Laborers 12 Sprinkler 2

Control ? Landscapers ? Tile Setters ?

DDC ? Masons ? Watchmen ?

Electricians ? Operators ? Windows 2

Elevator ? Painters Totals:

Visitors to the site

There were few casual visitors to the site, which is of no special interest to tourists. However, there were a few onlookers who observed the site from safe points established by the contractor. Besides students, there were visiting members of the contractor team such as off-site supervisors, engineers, and other supervisors. Day laborers comprised the bulk of the people entering the construction areas. DeMatteis/Turner is the contracting company, and they maintain strict safety standards. Because of the historic and high visibility of their work, the company is careful to ensure visitor safety, and make all feel welcome. The project has as much transparency as possible for one of this scale and scope.

Tests/Inspections

One of the most important inspections performed on the construction site was related to fire and emergency safety. The fire department (FDNY) repeatedly visits the site to ensure that engineering and architectural specs meet city safety standards for emergency evacuations. Because of the scale of the project, and the number of residents expected, it is important to maintain as many exit corridors as possible. The on-site project manager explained some of the other safety and quality inspections that are carried out regularly, especially those on concrete integrity and electrical wiring. The chief architect comes once per month to ensure design specifications are being met. The project is...

The welder had a fire watch personnel observing, and the supervisor ensured us that safety protocol was being followed.
Accidents, Injuries, or Unusual Events

Accidents and injuries are prevented via safety standards such as always wearing a hard hat in the construction area. There have been no severe injuries during the current project. Minor injuries are attended to in a medical tent. The only unusual event happened during the first phase of the project, when one of the scaffolds was unstable and partly collapsed but no one was injured.

Progress of Work

Key Activities and Material Deliveries

The project has been divided into five phrases, and is currently near the end of Phase III.

Most material deliveries take place early in the morning, but may occur at any time when materials are required.

Electrical wiring is still being installed, and there remains some work to do in this area.

Scaffolding is almost all in place, and is becoming unnecessary in some areas that are ready for finishing.

The most important activities remaining are focused on design and aesthetics. The structure of the project is nearly in place. Final elements, especially interior elements, need to be introduced. Windows need to be installed. Stairs are not yet complete.

Items Accomplished

The frame of the building is almost fully intact and stable, with metal, concrete, and wood elements in place.

Electrical wiring is almost finished, and good progress has been made.

Meetings and Significant Decisions

Meetings will be taking place with increased frequency as the project nears completion. The contractors will be working with a more extensive team including architects and designers when it comes to Phases IV and V. These phases are more aesthetic than structural in nature, but the construction contractors are still needed at these phases to ensure integrity of the project.

Unresolved Issues / Factors Contributing to delay

There are…

Cite this Document:
Copy Bibliography Citation

Related Documents

Construction Industry in Iran -
Words: 1766 Length: 5 Document Type: Case Study

E. Sharpe, Inc., 1997. Gambatese, John a. "Liability in designing for construction worker safety." Journal of Architectural Engineering: September 1998: 107-112. Gitter, Robert J. "Wage Subsidy Programs in Apprenticeship Training in the Construction Industry." Journal of Vocational and Technical Education Fall 1985: 3-10. Gould, John P. And Bittlingmayer, George. The Economics of the Davis-Bacon Act: An Analysis of Prevailing-Wage Laws. Washington D.C.: American Enterprise Institute of Public Policy Research, 1980. Korman, Richard, Kohn, David

Construction Industry in Iran: Problems
Words: 3643 Length: 10 Document Type: Literature Review

Building Materials If one is going to build a home or a business, one needs good materials with which to construct those dwellings. However, most of the materials that are used in construction projects in Iran are far from meeting international standards (Babai, 2011). They are of a low quality, and they do not hold up in the way that they would if high quality materials had been used. Many of

Construction Project Risk Management Objective
Words: 2429 Length: 8 Document Type: Research Paper

"Brainstorming, scenario planning, and expert interviews is the tools highway engineers commonly use in routine engineering and construction management tasks." (U.S. Department f Transportation 2007 P. 2). Table 3 reveals the summary of the tools and technique in the risk identification process. Table 3: Risk identification tools and techniques PROJECT-SPECIFIC DOCUMENTS PROGRAMMATIC DOCUMENTS TECHNIQUES Project description Work breakdown structure (WBS) Cost estimate Construction schedule Procurement plan Team issues and concerns Historic data Checklists Final project reports Risk response plans Organized lessons learned Published commercial databases Academic

Construction Industry in Iran: Current
Words: 1400 Length: 5 Document Type: Data Analysis Chapter

This would help to cut costs, and was seen as a significant problem as evidenced by the table on page 2. Another important issue was the consequences of using construction material that is substandard, meaning that the materials may be more difficult to work with and they not be as reliable and durable. Most individuals did not want to use these products, but there are often no other choices.

Construction Risk Management of Channel
Words: 1856 Length: 7 Document Type: Term Paper

In addition, Sound Transit has installed eight sensing devices for the building, including probes that would register any soil shifting at the tunnel depth. Such alerts would allow Sound Transit time to apply extra grout between the tunnel and the apartment building's basement. 6. Output Analysis and Discussion Here, Sound Transit has taken reasonable and economically feasible precautions to reduce the risk of damage from soil sliding. At this point, the remaining

Construction Contracting Partnering Agreement This Partnering Agreement...
Words: 580 Length: 2 Document Type: Essay

Construction Contracting PARTNERING AGREEMENT THIS PARTNERING AGREEMENT (this "Agreement"), is entered into on ____, by and between Capitol Home Improvement, LLC ("Capital Home Improvement") and The KEIMA CONSTRUCTION Corporation ("KEIMA CONSTRUCTION"). WHEREAS, KEIMA CONSTRUCTION represents that it has expertise in the area of [specify area of expertise of which partner is sought], and is ready, willing, and able to provide assistance in that area to CAPITOL HOME IMPROVEMENT and to the client of

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now