Project Management
Scope Management
Small LAN's Inc. installed a Local Area Network at the new Spring Academy Childcare Center. The project came in a few weeks late becaue of a failure in the planning procees and the overall partner's communications. "In directing the intent of the project, the plan must clearly identify the project objectives, goals, and any special influences or constraints on the project scope." (Stuckenbruck, 100) In order to compete in the twenty first century, Small LAN's Inc. turned in a rather low bid to acquire this work and with today's tighter corporate budgets and reduced resources, Spring Academy Childcare Center accepted.
For this particular project, the project scope consisted of Small LAN's Inc. taking the lead in purchasing all necessary equipment and then professionally installing an entire network over the course of twenty three days. The project had a start date of May 17, 2002. The deadline was set because the school's director wanted the new network and computer lab in place prior to the summer camp starting on June 10, 2003.
The Local Area Network required a rewiring of the school building and Small LAN's Inc. was not qulaified to do that part of the job. The Spring Academy Childcare Center's director recommended his brother-in-law who was a private contract electrician. The relative was evetnually hired to do the required building re-wiring.
The installation was to include a server in the main office, eight PC's (one in each classroom, one in the director's office and one at the receptionist station), two centralized network printers (one on the first floor and a second on the second floor), and five additional PC's with a color laser printer in the upstairs computer lab.
The purpose of the WBS is to break the total project down into sufficiently small subdivisions to permit accurate cost estimates, and to permit adequate visibility and control. A second purpose of the WBS is to ensure that the smallest subdivisions represent tasks that can be readily accomplished within the estimated cost and schedule. (Stuckenbruck)
The Work Breakdown Structure was created by the Small LAN's Inc. project leader but he never consulted the outside contractor for his input.
The Work Breakdown Structure
100 Inspect the building structure
110 Contractor Evaluation
111 Get Building Blue Prints
112 Inspect Walls
113 Township Building Codes
114 Assess Permits (On Going)
200 Design Network
210 Planning Stage
211 Meet With Contractors
212 Transfer Needed Building Code information
220 Blue Print Grid Creation
221 Use Building Codes to Design Wiring Layout
222 Sketch Grid
230 Hardware Design
231 Server Specs
232 PC Specs
233 Printer Specs
240 Blue Print Grid Approval
241 School Director to Sign
300 Purchase cabling
310 Purchase Stage
311 Negotiate Wiring purchases
312 Set Delivery Date
400 Install cabling
410 Installation Stage
411 Receive Wiring
412 Test Wiring
413 Install Wiring
500 Purchase Hardware/Software
510 Installation Stage
511 Receive Hardware
512 Test Hardware
513 Install Hardware
600 Set Up Server/Hubs
610 Installation of Networking Software
611 Load Software
612 Connect Nodes (all PC's & Printers)
613 Configure Network Software
614 Configure Workstation PC's Software
615 Configure Printers
613 Test Network
700 Stress Test System
II. Time Management And Gantt
Setting deadlines and insuring that the project was in a position to meet deadlines was done by Small LAN's Inc. For this particular project, time was a major factor to measure the success or failure of the project by the main stakeholder Spring Academy Childcare Center. The center had an obligation to have the new Local Area Network fully functioning in time for the beginning of their summer camp program that was scheduled to open on June 10, 2002. Training was planned for the first week of camp so that the teachers would have free time to learn the intracies of the system. "The project Master Schedule interrelates all tasks on a common time scale. For a simple project the project Master Schedule may consist of a simple bar or Gantt chart." (Stuckenbruck, 108)
Deadlines were established throughout the planning stages by Small LAN's Inc.. Tasks were created from the working breakdown structure. From the task list, a simple Gantt chart was created but not shared with the electrician contractor who had also hired one addtional peer to assist with the wiriring. A Gantt Chart greatly increases the chances of meeting established deadlines because the tasks can be assigned and a date can be tied to the task.. Unfortunately, on this project there was some float that did not get adjusted so the overall project ended up being completed behind schedule.
Effective planning requires a concentration...
Practice Fusion Strategic Planning Document: A Plan for Conversion, Integration, and Implementation of Electronic Health Records (EHR) in a Residential Care Facility Description of Institute The objective of this study is to examine the implementation of a new information technology data-management plan at a residential care facility for individuals with mental illness/mental retardation. This facility also provides day treatment and respite care. This will include a two-person practice for a Nurse Practitioner and a
The following diagram represents the structure of the idea. Figure 2. Project flow pursuant to Plan Abu Dhabi 2030: Urban Structure Framework Plan Objectives of the Study The overarching objective of this study is to build a solid portfolio management application that connects all the local governments of Abu Dhabi emirates in ways that will allow them to collaborate on various projects pursuant to Plan Abu Dhabi 2030 through one unified system
Role-based ERP systems are critical for the siloed, highly inefficient architectures of legacy ERP systems to be made more relevant, contribute greater financial performance, and lead to higher levels of overall customer satisfaction. c. Purpose of the study The purpose the study is evaluate how enterprises who adopt role-based ERP system implementations are able to attain higher levels of financial and operations-based performance vs. those that rely on silo-based, more functionally
66). Furthermore, social software will only increase in importance in helping organizations maintain and manage their domains of knowledge and information. When networks are enabled and flourish, their value to all users and to the organization increases as well. That increase in value is typically nonlinear, where some additions yield more than proportionate values to the organization (McCluskey and Korobow, 2009). Some of the key characteristics of social software applications
Ayers (2000, p. 4) describes a supply chain as "Life cycle processes supporting physical, information, financial, and knowledge flows for moving products and services from suppliers to end-users." A supply chain can be short, as in the case of a cottage industry, or quite long and complex as in the manufacture, distribution, and sales of automobiles. In fact, the automobile supply chain has its origin in the mining of the
PC's, Central-System Computing, and Government Functionality In this article, the authors use correlational methods to prove their point-of-view. The way that this is accomplished is through a survey. They used percentages comparing two sets of subjects as well as a statistical analysis based on Cramer V scoring. The importance of the correlation was based upon whether or not the values in the study were greater than.20 on the Cramer V scale.
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now