Natural Soup Project
PROJECT STATUS REPORT
Currently the Natural Soap Project is roughly halfway through its planning phase. Thus far it has already experienced some losses of technical resources which has caused delays as well as anxieties. This analysis will provide a project status update.
MILESTONE CHART
Work
Duration
Start
Finish
% Work Complete
Project Planning
112 hrs
Wed 10/7/15
Mon 10/26/15
Technical Team
112 hrs
Wed 10/7/15
Mon 10/26/15
Requirements
hrs
Wed 11/11/15
Manufacture Soap
hrs
Thu 11/12/15
Mon 12/14/15
Testing
hrs
Deployment
hrs
Wed 12/16/15
Wed 12/16/15
SUMMARY OF PERFORMANCE
SUMMARY OF RISKS AND ISSUES
Highlights of Risks
Anxiety among members of the technical team
Competition could potentially launch 3 months earlier
Placed other projects at risk due to borrowed assets
Highlights of Issues
Loss of two key technical resources
day delay
DISCUSSION
Risk is defined as an event that has a probability of occurring, and could have either a positive or negative impact to a project should that risk occur. Project risk is one of the hardest project components to plan for and the project contains significant risks as well as already being behind schedule. One option would be to attempt to develop a crash schedule. In this case, the fundamental consideration to be made is whether the costs from crashing the project in such a significant manner exceed the benefits to be gained by having the project completion scheduled and if there are enough resources available to achieve the desired outcome. However, given that the project is already behind schedule and one of the risks includes the fact that a competitor might bring their product to market first, a crash schedule might be a viable option. Furthermore, since the project's projected end date is during the holiday season, it is likely that sales could increase if the product was brought to market earlier.
There also exists a trade-off consideration between quality and schedule that may pose problems to the viability of the finished product. For example, a crashed schedule could produce an inferior product. Another conceivable risk is that the project will increase its budget and resources significantly, while also failing to meet the deadline. Thus the company might have to accept both the costs of the project's crash schedule while in turn losing the revenue that would have been produced by the soap being on the market during the holiday season.
You’re 82% through this paper. Sign up to read the full paper.
Sign Up Now — Instant Access Already a member? Log inAlways verify citation format against your institution’s current style guide requirements.