Natural Soup Project
PROJECT STATUS REPORT
Currently the Natural Soap Project is roughly halfway through its planning phase. Thus far it has already experienced some losses of technical resources which has caused delays as well as anxieties. This analysis will provide a project status update.
MILESTONE CHART
Work
Duration
Start
Finish
% Work Complete
Project Planning
112 hrs
Wed 10/7/15
Mon 10/26/15
Technical Team
112 hrs
Wed 10/7/15
Mon 10/26/15
Requirements
hrs
Wed 11/11/15
Manufacture Soap
hrs
Thu 11/12/15
Mon 12/14/15
Testing
hrs
Deployment
hrs
Wed 12/16/15
Wed 12/16/15
SUMMARY OF PERFORMANCE
SUMMARY OF RISKS AND ISSUES
Highlights of Risks
Anxiety among members of the technical team
Competition could potentially launch 3 months earlier
Placed other projects at risk due to borrowed assets
Highlights of Issues
Loss of two key technical resources
day delay
DISCUSSION
Risk is defined as an event that has a probability of occurring, and could have...
Project Management in a Legal Context Project management is increasingly becoming a popular and preferred way of contending with inter-organizational ventures that are out of the ordinary. When the functions of a project require the involvement of specialized personnel and skill sets which may not be readily represented from within the company to the fullest extent demanded, it may be appropriate to organize a project team. This might be comprised of
Project Management February J. 2014 A project is a temporary group of activity designed to produce unique products and services or results. Typically, a project has a defined beginning and end and therefore having defined scope and resources. (Pierre, 2012). A project also has a specific set of operations to accomplish a singular goal. Examples of projects are as follows: Development of software to improve business process, Construction of bridge or building, Expansion of sales
Project Management In order to define project management, one must first define what is a project. A project is a temporary activity performed by a group in order to develop a unique service, product, or result. A project is labeled a temporary activity because it has a defined start and end in time. Therefore, a project has a defined scope and resources. This means that a project can only be carried
Project Management: Case Study in Managing a Complex Shipyard Project in Singapore Background of Complex Shipyard Construction Project Company background Project Overview and Objective Work Process of Building Construction Issue Analysis in Shipyard Construction Project Management Literature Review of Project Management Issues in Scope Management Methodology of Scope Management Lessons Learned from Scope Management Issues in Cost Management Methodology of Cost Management Lessons Learned from Cost Management Issues in Human Resources Methodology of HR Management Lessons Learned from Human Resource Management Case Study in Managing a
Balanced Scorecard Flexibility One of the characteristics of the balanced scorecard model is that it is largely flexible and easy to customize to fit a wide range of different applications in a variety of different industries. The Tesco 'Steering Wheel', for example, includes the four main components but then adds a fifth perspectives -- capturing their commitment to the community in addition to their tradition balanced scorecard metrics along the lines
Health and Safety in Construction Industry The construction industry is by far the most dangerous one as it takes more lives every year and results in many short- and long-term minor or severe injuries. The UK government regulatory bodies have been playing a significant role in ensuring that proper health and safety procedures are followed. Throughout the last four decades, its role has been impeccable in decreasing fatalities in the construction
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now