Verified Document

Project Management And Management Term Paper

Project Management Notebook This report provides a resourcing plan, a risk management plan, as well as a leadership and management plan for a three-day music festival to be held in Country Victoria during the 2016 Australia Day Weekend. The report also discusses the chosen approach for each plan, clearly highlighting why other alternatives may not be suitable for this type of project.

Resourcing Plan

Project resources generally fall in three categories: labor (human resources), equipment and facilities (such as machinery and venue) and materials (consumables such as stationery) (Thomsett, 2010). The type and quantity of resources required in each category is often determined by the nature and complexity of the project (Winch, 2010). A complex project such as an infrastructure construction project, for instance, would require more permanent staff and sophisticated equipment due to the time-consuming and resource-intensive nature of the project. However, a less complex project such as a three-day music festival would require volunteers, temporary staff, and less equipment.

Even so, determining the amount of resources required to accomplish a project may often be a daunting task for the project manager regardless of its character and complexity (Kloppenborg, 2015). The project manager may adopt from a number of approaches to estimate resource requirements. These include expert judgment (getting opinions from experts in the field); alternative analysis (weighing different alternatives of assigning resources); published data (relying on relevant articles, journals, periodicals, and books); bottom-up estimating (breaking down the project into smaller activities and determining the resources required for each activity); and historical data (getting data about similar projects done in the past) (Young, 2013).

In the case under consideration, relying on historical data presents the most suitable approach for estimating resource requirements. Since the Australia Day Weekend is held annually, data about festivals held in previous years can readily be obtained. There is less likelihood that this year's event would be significantly different from the previous ones. Previous data obviously can tell the average number of attendees to expect as well as the stakeholders and suppliers involved. Relying on historical data would help minimize the time and effort required in making resource estimations (Young, 2013). More importantly, a music festival project is not complex to the extent that it would require more sophisticated approaches such as bottom-up estimating, published data, and expert judgment, which usually involve more time, effort, and costs.

A three-day music festival expected to be attended by approximately 8,000 to 12,000 is a large event. Some of the key resources that will be required include volunteers, masters of ceremony (MC), security officers, a public address system, venue, banners, stationery, cars, garbage bins, as well as food and beverages. Appendix 1 provides a detailed description of the resources that will be required for the festival. The resourcing plan outlines not only the type of resources that will be required, but also their importance and where they will be obtained.

Risk Management Plan

Risk management is an important area of the project management body of knowledge (Project Management Institute [PMI], 2013). Any project, regardless of size and complexity, presents risks, which if not properly managed can result in unforeseen consequences. The first step in developing the risk management plan is to identify the possible risks (Lock, 2007). One of the most appropriate ways of achieving is to rely on past experiences, either the project manager's experiences, or experiences of similar events (Winch, 2010). As mentioned earlier, the Australia Day Weekend is a regularly held event. Therefore, knowledge of the risks associated with the event is readily available. For instance, risks common to such an event include chaos, theft, injuries, fire, traffic accidents, food poisoning, as well as unexpected changes in weather. Again, relying on past experiences would minimize the time and effort required in risk identification.

Risk identification is followed by risk evaluation in terms of likelihood and impact (PMI, 2013). This enables the project manager to prioritize the (most and least important) risks. Generally, risk evaluation process may take the quantitative or qualitative approach or a combination of both (Kloppenborg, 2015). Quantitative risk analysis entails the use of quantitative techniques such as sensitivity analysis, decision trees, and Monte Carlo analysis to evaluate the possibility and severity of the risks associated with a project (Meredith and Mantel, 2011). These techniques are often suitable for large, lengthy, and complex projects such as infrastructure construction projects, not for less complex and short duration projects like the three-day music festival (Thomsett, 2010).

Qualitative techniques would be more appropriate for the festival. The suitability of this approach for this project is particularly informed by the fact that risk identification will mainly be based on historical data. Past experiences can readily reveal the most common risks in such events and their possible outcomes. Qualitative risk analysis basically entails subjective evaluation of the probability and impact of the various risks on a defined scale (Meredith and Mantel, 2011). In this case, risk probability and impact will be evaluated on a scale of 1 to 5, with 1 representing least likely or least impact and 5 representing most likely or...

The scores for probability and impact are then multiplied to determine the weight of the risk. After evaluation, measures for avoiding or minimizing the risks are then identified. Responsibilities for risk management are also assigned. Appendix 2 identifies the major risks associated with the event, their likelihood and impact, measures for avoiding or minimizing them, as well as individuals responsible for managing the risks.
Leadership and Management Plan

The success of any project is largely dependent on its effective management (Kloppenborg, 2015). Generally, project leadership and management may take the authoritative, coercive, or democratic approach (Lock, 2007). In the authoritative approach, the project manager articulates the vision of the project to the entire team, but permits team members to collaborate in coming up with solutions. This can be a great way of motivating project team members as individual contributions are valued (Meredith and Mantel, 2011). In the coercive approach, however, the project manager's directions must be followed without questioning. Though this approach minimizes the likelihood of errors, it may hinder creativity and reduce team morale. As for the democratic approach, the project manager creates an atmosphere where every team member has a voice in decision-making. Though this approach may result in time wastage due to lack of consensus, it often boosts morale among team members, and thereby success of the project.

It is important to note that there is no one-size-fits-all approach for project management. Nonetheless, project success is usually more guaranteed when the project manager can effectively blend the various approaches (Kerzner, 2009). For instance, while democracy is important, the project manager must at the same time be authoritative enough to ensure tasks are accomplished without fail. In this case, a blend of the authoritative and democratic approach would be important. It will be important for the project manager to clearly share the vision of the project with the project team, while at the same time allowing different ideas and perspectives.

An important aspect of project leadership and management relates to the project team structure, which basically depicts the organization of the project team (Berkun, 2008). A simple structure as shown in figure 1 below will be sufficient for the event. Appendix 3 describes the roles and responsibilities of the project team.

Figure 1: Project team structure

References

Berkun, S., 2008. Making things happen: mastering project management. Sebastopol, CA: O'Reilly.

Kerzner, H., 2009. Project management: a systems approach to planning, scheduling, and controlling. 10th edition. Hoboken: Wiley.

Kloppenborg, T., 2015. Contemporary project management. 3rd ed. Boston: Cengage Learning.

Lock, D., 2007. Project management. Burlington: Gower Publishing.

Meredith, J. and Mantel, S., 2011. Project Management: A managerial Approach. Hoboken: John Wiley & Sons.

Project Management Institute (PMI), 2013. A guide to the project management body of knowledge. 5th edition. U.S.: Author.

Thomsett, M., 2010. The little black book of project management. New York: AMACOM.

Winch, G., 2010. Managing Projects. Iowa: Blackwell Publishing.

Young, T., 2013. Successful project management. 4th edition. London: Kogan Page.

Appendices

Appendix 1: Resourcing Plan

Resource Type

Details

Activity/Role

Source

Labor

Project team

• Coordinating activities

• Training and supervising volunteers

• Event marketing

• Ticket sales

• Documentation

• Facilities management

Recruitment from referrals

Volunteers

• Coordinating traffic

• First aid administration

• Assisting and directing attendees

• Stage management

Recruitment from existing volunteer databases

Masters of ceremony

• Hosting the event

• Making important announcements

Referrals

Security officers

• Screening attendees

• Crowd management

Security company

Entertainers

• Entertaining the audience

Popular bands, musicians, and performers

Equipment and facilities

Auditorium

• Venue for the event

Local auditorium

Public address system

• Audibility and announcements

Suitable supplier

Toilet facilities

• Disposal of urine and feces

Venue and mobile toilets

Accommodation

• Housing important guests

Local hotels

Garbage bins

• Garbage management

Suitable supplier

Walkie-talkies

• Communication

Suitable supplier

Ambulance

• Emergencies

Local hospitals

Vehicles

• Transport and mobility

Car hire company

Parking lot

• Vehicle parking

Nearby public spaces such as schools and playgrounds

Materials

Tickets

• Revenue collection

Online

Banners and posters

• Publicizing the event

Suitable supplier

Activity programs

• Show schedule of events

Suitable supplier

Stationery

• Writing and printing

Suitable supplier

T-shirts

• Recognition of important personnel

• Additional revenue

Suitable supplier

Badges

• Recognition of important personnel

Suitable supplier

Food and beverages

• Feeding guests and attendees

Suitable supplier

Appendix 2: Risk Management Plan

Risk

Likelihood

Impact

Weight

Strategy

Responsibility

Theft of cash…

Cite this Document:
Copy Bibliography Citation

Related Documents

Project Management Plan
Words: 2954 Length: 11 Document Type: Research Paper

Project Management Plan of a New Restaurant This project management plan is majorly concerned primarily with the first two steps which are defining the project; the project objective is broken down into a series of manageable steps called tasks and designing the project process; this work is performed by the project manager and is presented in the GANTT chart where the tasks are displayed in more detail (Hamilton, 2004). Besides, for

Project Management in a Legal Context Project
Words: 1301 Length: 5 Document Type: Essay

Project Management in a Legal Context Project management is increasingly becoming a popular and preferred way of contending with inter-organizational ventures that are out of the ordinary. When the functions of a project require the involvement of specialized personnel and skill sets which may not be readily represented from within the company to the fullest extent demanded, it may be appropriate to organize a project team. This might be comprised of

Project Management February J. 2014 a Project
Words: 2863 Length: 9 Document Type: Research Paper

Project Management February J. 2014 A project is a temporary group of activity designed to produce unique products and services or results. Typically, a project has a defined beginning and end and therefore having defined scope and resources. (Pierre, 2012). A project also has a specific set of operations to accomplish a singular goal. Examples of projects are as follows: Development of software to improve business process, Construction of bridge or building, Expansion of sales

Project Management Involved in Formation of Airbus A380
Words: 3616 Length: 10 Document Type: Research Paper

Project Management Involved Formation of Airbus Project Management involved in Formation of Airbus The report investigates factors that led to the A380 project crisis. Analysis of the project revealed that Airbus did not integrate an effective project management model into the project lifecycle leading the project to be two years behind schedule, which eventually led to the costs escalations. The report reveals several lessons to be learned from the A380 project crisis.

Project Management Organizational Structures a Project Is
Words: 1286 Length: 4 Document Type: Essay

Project Management Organizational Structures A project is a variety of jobs that relate and point towards a critical solution. For a project to function successfully, money, time, resources, and personnel is required. Project management often dictates control of resources together with planning the intended project and designating resources in areas where they are needed. Before the start of a project, the management decides upon which organizational structure will be effected to

Project Management AT&T Is a Leader in
Words: 1089 Length: 3 Document Type: Case Study

Project Management AT&T is a leader in communication technology that connects people all over the world. Just as their customers and business depend on them and their services to remain connected, AT&T depends on the internal resources they have particularly project and program managers so that they can remain as the best service providers. Huawei is a Chinese Telecom giant that deals with products such as fixed-line communications, optical transmission, mobile

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now