¶ … MS Project
What was the original project duration prior to resource leveling? (Week 5 (1) file is the WBS before leveling)
In MS Project, a report was run to find the project's total duration. The total duration of the project before the resources were leveled was 140.73 and this made the expected project completion date April 9th, 2012.
What was the revised project duration after resource leveling? (Week 5 (2) is the WBS after leveling)
After the resources were leveled another report was run. This time the duration was calculated to be 84.75 days with a 55.96 day variance.
Carefully read the resource leveling...
Thirdly, having the ability to motivate the project team is a characteristic of a project manager. Projects can have ups and downs for the project team. When target dates seem far from reach, having a project manager with the ability to motivate the group by setting smaller goals and giving incentives can improve the team's morale. Communicating when things go well instead of only talking about the negative can
Project Management-7 What is the difference between a task dependency and a task constraint? The difference between a task dependency and a task constraint is apparent in the time. A task dependency connects two tasks by suggesting that one task will start comparative to another task, whereas a task constraint places the connection directly to a time rather than base it off the time when another task begins (Marmel and Muir, 2007). Give
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now