d) the efficiency of the project can be increased by crashing other activities in addition to creating the guest list and purchasing the food. Annie can crash activities like buying decorations and planning the menu. By crashing the buying of decoration Annie reduces the costs of the project by $70 and its duration by 2 hours. It is also recommended to crash this activity because it does not depend on the number of guests and it does not influence other activities. By crashing of the planning of the menu activity, Annie reduces the cost of the project by $60 and its duration by one hour. This activity influences activities like purchasing of food, and preparing it. Therefore, the reduction of planning the menu can help increase the efficiency of purchasing and preparing the food.

In addition to this, Annie can also crash the sending of invitations activity. This can reduce the costs of the project by $25 and its duration by one hour. The activity regarding sending the invitations does not influence the following activities of the project. Therefore, it is recommended to crash this activity in order to reduce the financial resources that this project requires. The money saved using this strategy can be spent on improving other issues.

This strategy can be applied to most projects, regardless of their objectives or size. It is important that project managers try to reduce the costs associated to projects' activities, but also their duration. By crashing certain activities, project managers can save important resources (Meyer, 2002). However, it is recommended to thoroughly analyze the effects of this strategy. This is because some of projects' activities cannot be crashed because they have significant effects on the quality of the project. Therefore, it is important that managers have the ability of determining which activities can be crashed.

e) by crashing the activities of the project Annie can save $480. Annie saves 12 hours by crashing the project. If she saves $40 for every hour reduced from the project, than this leads to $480. Annie wants to use this money she saved by crashing the activities of the project for buying a better present for her sister Gwendolyn.

This is a good example of the importance...

The example reveals how important amounts of money can be saved by crashing these activities. In addition to this, by crashing some of projects' activities, the timing of the project can be reduced. There are also other objectives that can be reached by this strategy. For example, in certain cases where the financial resources do not suffice in order to develop the project according to its schedule, other activities can be crashed in order to save some money that can be allocated to activities that require it. There are also situations where different factors determine a series of delays of certain activities, causing a long duration of the project than established. The effects of these factors can be counteracted by crashing certain activities and saving important amounts of time. The crashing of certain project activities should be performed in accordance with time management principles.
f) the duration of the fully crashed project reaches 18 hours in comparison with the duration of the project at its normal duration that reaches 30 hours. Therefore, Annie can save 12 hours. The amount of time saved can be used for looking for a gift that Annie wants to buy her sister. This example can be used by project manages and by other individuals that want to learn how they can improve the scheduling of projects and how they can better use their resources. It is important that such practices are used in accordance with the objectives of the project in case. Therefore, project managers should develop strategies that focus on improving the efficiency and productivity.

Reference list:

1.Meyer, B. (2002). Project Costs and Crashing. Management of Operations. Retrieved February 11, 2012.

Install exterior siding

Install wiring

Install roof

Erect wall frames

Preassemble wall frames

Concrete curing time

Pour concrete foundation

Install rough plumbing

Prepare site

Level yard

Landscape yard

Paint exterior

Paint interior

Windows

Hang drywall

Install insulation

Install exterior siding

Sources used in this document:
Reference list:

1.Meyer, B. (2002). Project Costs and Crashing. Management of Operations. Retrieved February 11, 2012.

Install exterior siding

Install wiring

Install roof
Cite this Document:
Copy Bibliography Citation

Related Documents

Operations & Quality Management Operations
Words: 1570 Length: 5 Document Type: Essay

References: Brinlee, D., MRP inventory management, Inventory Management, http://www.askdeb.com/inventory-management/mrp / last accessed on February 7, 2012 Heathfield, S.M., How to change your culture: organizational culture change, About.com, http://humanresources.about.com/od/organizationalculture/a/culture_change.htm last accessed on February 7, 2012 Johnson, R.W., Phased retirement and workplace flexibility for older adults: opportunities and challenges, Focus on Workplace Flexibility, http://workplaceflexibility.org/images/uploads/program_papers/johnson_-_phased_retirement_and_workplace_flexibility.pdf last accessed on February 7, 2012 Reh, F.J., Managing change: managing people's fear, About.com, http://management.about.com/cs/people/a/MngChng092302.htm last accessed on February 7, 2012 2010, ERP

Managing Quality With Six Sigma
Words: 1571 Length: 6 Document Type: Research Paper

The Improve Phase of the DMAIC process is also essential for managing the piloting and testing of the Six Sigma solutions discovered. It is also essential during the new product development process for measuring and quantifying the unique value proposition of the product or service being produced as well. The final phase, Control, is essential in both a Six Sigma and new product introduction process as well (Pestorius, 2007). Conclusion The

Supply Chain Management Hypothesis Defined Concepts of
Words: 24788 Length: 80 Document Type: Thesis

Supply Chain Management Hypothesis defined Concepts of SCM and the evolution to its present day form Critical factors that affect SCM Trust Information sharing and Knowledge management Culture and Belief -- impact on SCM Global environment and Supply Chain management "Social" and "soft" parameter required for SCM Uncertainties This chapter aims to give an outline and scope of the study that will be undertaken in this work. The study lays out the issues faced by manufacturing organizations when it comes

Operations Management in the United Arab Emirates
Words: 2440 Length: 6 Document Type: Essay

Operations Management in the United Arab Emirates The orchestration of resources, systems and processes across an enterprise to consistently deliver high-quality products that are profitable is the catalyst of Operations Management (OM). One of the most multi-disciplinary and multifaceted disciplines of management science, OM encompasses the new product development and introduction (NPDI) processes, supply chain systems and procedures and their orchestration to delivering profitable, high quality products (Fisher, 2007). When enterprises

Operations & Quality Management Discussion
Words: 1562 Length: 6 Document Type: Case Study

For instance, it requires increase space for storage. Then, it has to purchase technologies to help manage the inventory, as well as the supply and demands. Then, it would have to purchase trucks and other transportation machineries, and would also have to allocate budgets to completing the transport operations. The operations would have to be continually developed and improved; the fleet would have to be continually maintained and renewed,

Supply Chain Management How Analytics
Words: 1220 Length: 4 Document Type: Discussion Chapter

This dynamic is more than an experience effect or network effect, as it is multiplicative across the many members of the supplier network, in effect creating an entirely new platform for sharing knowledge and information. The reliance on analytics for creating the necessary integration links and platforms for decision making also dominate this phase of maturity in any supply chain network (Wang, Huang, Dismukes, 2004). With the findings that what

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now