Verified Document

Managing Building Construction Projects In Research Paper

Unavailability of professional construction management

6

2.12.9 Construction Delay: Quantitative Analysis

In some studied already done in issue with comstruction management, one of the main objectives of (Al-Momani, 2000) was to figure out the cause and degree of interruptions in public projects in Iran. Some of these studies investigated the causes of these interruptions for about 130 projects, counting office and communication facilities administration buildings residential buildings, schools, medical and centers. The sample population was recognized by choosing 130 ended public projects in diverse areas of Iran among the years of 1990 and 1997. To examine why construction delays and issues occurred, the succeeding statistics were gained from the projects' records:

ae Planned period of contract ae Actual conclusion statistics

ae Design variations

ae Disagreements

ae Warnings

ae Date of notice to continue ae Delays come across throughout construction ae Conflicts connected to the drawings and stipulations ae Time postponements ae Late delivery of material and equipment

As shown in Table 3.4, the incidences for each limit in five dissimilar construction groups were delivered, and numerous projects were behind for numerous reasons. The study establish that the chief causes of postponement were deprived design, change orders, weather, site circumstances, late distribution, financial conditions, and upsurge in quantities. The main reasons of delay discovered in this study were poor design, change order and site and financial situations.

Table 3-4 Summary of the Inspected Projects Occurrence of Delay in Iran

Facility

Type

Poor

Design

No

Delay

Change

Orders

Weather

Increase in Quantity

Late

Delivery

Site

Condition

Economic

Conditions

Total

House

4

3

1

3

2

0

1

0

14

Office

8

5

5

4

5

1

2

4

34

School

10

14

8

6

3

4

5

2

52

Hospital

6

2

4

2

1

3

0

2

20

Roads

4

0

2

1

1

2

0

0

10

Total

32

24

20

19

12

10

8

8

2.13.10 Construction Delay: Developing Economy

(Ogunlan et al. 1996) displayed a certain survey which was able to look at the issues in construction management that were experienced while in the process of constructing high-rise buildings in Iran. Twelve projects were chosen for examination and meetings were presented with their main engineers. Interviews took place right there on the project sites, and a total 20 persons had been questioned, on behalf of 2.4 individuals per project. Candidates were allowable to effortlessly debate the details for their development's breaks and categorize the parties that were complicated. The facts of the origins of interruption can be seen in Table .

3.1 Poor ICT groundwork

If a construction site does not have an extensive and high quality ICT groundwork, it's not likely to exploit ICT power entirely. Some defendants consider that Iran's ICT infrastructure does not really permit them use their ICT devices with the entire volume. For instance internet speed is not really enough to be able have an online meeting by video conference, on the other hand, they could maybe be ready to have some kind video conference if the internet speed is a whole lot better. Furthermore, in some distant construction locations which are out of city parts, there is not much contact to internet. As a result, some innovator construction businesses in ICT who have enormous developments in distant regions, have to capitalize on ICT groundwork merely for that project and this substance forces an excess cost to them. One of the defendants specified "as a group we are driving on the ICT road. it's not conceivable to even drive fast on a road that is stony. If we have made the decision decided to go that route this way, the road should be paved."

3.2 Unacquaintedness of local personnel with ICT in remote construction sites

The staffs who are employed in construction sites are typically in lower level of field associated with office workers and this matter is simple for distant construction sites for the reason that discovering local experts is not continuously conceivable. As a result, the company have to give more to send specialists to distant construction sites. This subject is not cost functioning for small developments for the reason that a small project typically has a small income boundary and it is not defensible to capitalize a lot for sending accomplished...

The construction firms are the ones that usually make the attempt to upkeep their ones that are educated and experienced staff. As it was articulated, expert local workers are not typically obtainable to service in remote. construction locations. Teaching the local personnel is an answer merely for huge construction projects, for the reason that the local trained personnel of small developments will be jobless in that district after project conclusion and typically the gotten profit is less than cost of education.
3.4 Lack of sensation transfer in some electronic communication devices

It is clear that individuals really do show their goals with words. The words are marked otherwise in different circumstances. Each articulation comprises a precise feeling and resolution. One of the hindrances of electronic communication devices is that is really does show some sort of lack of feeling transfer. Video session is a communique instrument that is very helpful for those construction firms that are performing remote construction developments. Online meeting can decrease travelling price of personnel among head office and construction place. On the other hand, one of the respondents spoke that their corporation has the wanted ability for video conference, nonetheless the personnel don't really welcome these ICT devices. He made the point that it has a human motive. He mentioned "When the individuals are together, have more truthful sentiment about having a meeting than when they are in their own house. They have more reaction and action and meddling when they are composed."

3.5 Inapplicable software outputs

Engineering judgement has been a major issue when it comes to design procedure of every construction development. In the design stage it is really essential that knowledgeable and well-informed engineers strategy or supervise the design procedure. Their knowledge allows them to have an outstanding engineering judgement about applicability of design software productions. One of the software designers trusts that even if he deliberate structuring codes in their software as much as he can, on the other hand if the user had not adequate technical information, he/she cannot use the software properly.

It can be concluded that in the remote construction developments that designers are doing in main office and away from construction location, applicability of software productions will be reduced if the designers did not have sufficient experience and resourcefulness from implementation of the productions and if they want to visit and oversee the construction site, it will cost a lot to exchange among head office and construction location.

3.6 Complicated administrative process for ICT development

As it was articulated, in some circumstances, to progress the poor ICT groundwork, construction firms will really need to do some investment on ICT groundwork single for a specific project. Throughout the interviews, it was exposed that the managerial procedure of getting consent to improve some ICT groundwork like internet is extremely difficult. An applicant stated that "our business may be tangled numerous months to get consents." The interviewees really do have this assumption that it will cost less for the government to grow ICT infrastructure in distant construction sites for the reason that the expansion cost will be dispersed amongst all construction firms consuming these amenities. Then, each business has to participate distinctly on a precise project.

3.7 Poor reserve system in remote construction places

In the isolated construction developments, the corporation has to make sure that they launch two separate administrations, one in the head office and another in the construction location. Linking and assimilating these two governments is a vital task. For the duration of the investigation stage, it was unwritten that one of the construction supervisors' worries is basically the backup system. Because of lack of a combined system amongst major office and construction place the backup system will possibly be detached. One of the respondents made the point "we are the ones that do send the strategies to the construction places in arrangement of computer archives. If these various files are obtainable for contractor and supervision system deprived of any restraint, everybody will be able to make change on them consciously or involuntarily and these changed files can be measured as the unique plans"

CHAPTER THREE:METHODOLOGY

4.2.3 Recommendations to improve construction management in buildings

To be able to improve construction management in buildings, there is a lot of interventions and different procedures that Iran can take. Iran industries are on their way with experiencing an almost incessant efficiency growth in recent times. The one irregularity has been the construction business, for which general efficiency weakened from 1995 to 2001 (Triplett and Bosworth, 2004). For businesses other than construction, improved efficiency can actually be credited to developments in and augmented practice of information technologies, which are actually increased competition…

Sources used in this document:
Reference:

Acharya, N.K., Young, D.L., & Im, H.M. (2006). Conflicting factors in construction projects: Korean perspective. Engineering, Construction and Architectural Management, 13(6), 543-566.

Alaghbari, W., Mohd, R.A., Salim, a., & Ernawati. (2007). The significant factors causing delay of building construction projects in malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206.

Al-Kharashi, a., & Skitmore, M. (2009). Causes of delays in saudi arabian public sector construction projects. Construction Management and Economics, 27(1), 3.

Arditi, D., & Robinson, M.A. (1995). Concurrent delays in construction litigation. Cost Engineering, 37(7), 20-20.
Cite this Document:
Copy Bibliography Citation

Related Documents

Construction Project Risk Management Risk
Words: 2900 Length: 9 Document Type: Research Paper

5.4: Accept Bullring team accepted some risks; however, the company developed the effective cost and schedule strategies to manage these risks. For example, the company allotted sufficient fund to militate against risks associated with the project costs and schedule. Table 2 presents the compressive list all the risks deemed to affect the outcome of the Bullring project. Table 2: Associated Risks on the Project Cost Related Risks: Index Scores Tight project schedule 0.67 Design variations 0.49 Project variations from

Construction Project Risk Management Objective
Words: 2429 Length: 8 Document Type: Research Paper

"Brainstorming, scenario planning, and expert interviews is the tools highway engineers commonly use in routine engineering and construction management tasks." (U.S. Department f Transportation 2007 P. 2). Table 3 reveals the summary of the tools and technique in the risk identification process. Table 3: Risk identification tools and techniques PROJECT-SPECIFIC DOCUMENTS PROGRAMMATIC DOCUMENTS TECHNIQUES Project description Work breakdown structure (WBS) Cost estimate Construction schedule Procurement plan Team issues and concerns Historic data Checklists Final project reports Risk response plans Organized lessons learned Published commercial databases Academic

Construction Project Management the Focus
Words: 2119 Length: 8 Document Type: Research Proposal

(in its turn, the financial environment must be understood with reference to the wider economic situation.) Cost control is the activity which compares cost performance against the cost plan, adjusting one or the other dynamically by reference to the changing circumstances in the project's financial environment. (Hughes, 1991, p.1) 2. Time Control -. Timing is influenced by many environmental factors, but the client's attitude to the timing of the project

Project Leader for the Office Building Construction
Words: 1694 Length: 4 Document Type: Case Study

project leader for the office building construction project, formulate a vision statement for the team project. According to Gray and Larson (2008) a vision is unlike a project scope statement, which includes: budget, end dates, and performance requirements, a vision involve the less tangible aspects of project performance. It refers to an image a project team holds in common about how the project will look upon completion, how they will

Construction Projects and Construction
Words: 1143 Length: 2 Document Type:

Decision As the general contractor of a medium size, one of the most important decision points in construction is a go no-go decision. Go no-go decisions have become common in the modern construction industry because of the changing marketplace that has in turn generated complex procurement choices. In light of the changing marketplace in the construction industry, construction companies face new challenges in identifying the most suitable project proposals to

Construction Project Planning Phase Your Clients Have
Words: 646 Length: 2 Document Type: Term Paper

Construction Project Planning Phase Your clients have secured the financing to develop 48 acres land into mixed-use buildings. They have asked you to draft a high-level project plan to begin the more detailed discussions. Forty percent of the site is an undeveloped field, and the project must include a nursery school. Where should you begin? Based on your readings and your experience, identify the approach you would take to drafting this high-level plan. Describe

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now