Verified Document

London Olympic Stadium Essay

Construction of London Olympic Stadium Within the management-orientated system, the solution proposed is Construction Management (CM). Under the CM system, the Client employs an Architect and a Construction Manager, who oversees the works of individual Contractors (Smith, 2003). The system ensures that the Contractor and the Architect are put on an equal footing before the Client, and that the Construction Manager is able to provide design advice, particularly in regards to buildability. Compared to the Management Contracting (MC) system, the Client still enters in a contractual relationship with the Contractors (Masterman, 2002). This relieves some of the risk from the Construction Manager, and also allows the Client to better control the hiring process and the performance of the Contractors. This may be a key element in ensuring the timely and quality delivery of the Stadium project (Turner, 2005).

The organizational structure proposed is summed up below:

-level management

Project-level management

* Programme Manager does not have contractual links with other parties except for the Client.

Client

Manager

Architect (Concept Design)

Construction Manager

Contractor 1

Contractor 2

Contractor 3

Architect (Stadium Design)

The CM system can achieve the key objectives of Time and Quality in this project (Smith, 2003). Thus, CM has been associated with a 'prestige' level of quality, according to the Construction Round Table's guide to the building process, cited in Masterman. In addition, Masterman points out that research shows that on average, design and construction are completed more quickly than using conventional systems (Turner, 2005). The Cost of the project may be mitigated by increased competition and control over costs achieved if the employer enters direct contracts with contractors. Other advantages include a better working relationship within the project team and more constructive attitudes at managerial and operational levels (Masterman, 2002).

In regards to the payment mechanism, the project is complex and high profile; therefore, risk should be shared to some degree between the Client and the Contractor. The solution suggested is the use of a cost-reimbursable system, more specifically target cost (Turner, 2005). Cost-reimbursable systems are open-book accounting, based on payment of actual cost incurred by the Contractor plus overheads and profit. Amongst the cost-reimbursable systems, target cost is the more suitable for this project, as it could give a provisional indication of the final cost (Smith, 2003).

In accordance with CIRIA Report R85, cost-reimbursable contracts should be used in case of:

1.Inadequate definition of the work at the time of tender due to emphasis on early completion and/or an expectation of substantial variation in work content

2. Work of exceptional organizational complexity i.e. multi-contract situation, involvement with statutory undertakers and/or when access is restricted

3. Work involving technical innovation or exceptional technical complexity

4. Any other situation involving major unquantifiable risks to the Contractor, including effect of inflation, work below ground level and/or abnormal industrial relations

5. Some recurrent work

The Architect for the in-depth design would generally be expected to work in parallel with the Construction Manager and some of the Contractors; the estimation of proper Bills of Quantity might be difficult at the beginning (Smith, 2003). The specific requirements of the Client, the problematic ground conditions, and issues related to the inflexibility of time and quality standards may cause substantial variation (defined by CIRIA R85 as more than 15-20% of the tender price). Organizational complexity is present through multiple contracts; access might also be a problem due to the ongoing works on several adjacent sites (Masterman, 2002). Technical innovation and technical complexity are also issues to consider, as the stadium's design must reach iconic level and allow for the later conversion into the 25,000 seat permanent stadium. CIRIA R85 also argues for the cost-reimbursable payment system when the Client has a particular interest in maintaining good labor relations, which is an important aspect...

Disadvantages of target costing include agreement on when to adjust the target or setting the target at an unrealistic low level. To mitigate this, the partnering charter should include provisions for target adjustment, while the competitive dialogue tendering system outlined below could avoid setting an unrealistically low cost level (Smith, 2003).
In the event that there were any cost increases that were seen as non-recoverable then they managers had to go to the government and get a release of contingency, referring to the £2bn pot that had been set aside for overspend. They were not able to seek any release of contingency, but clearly they were not immune to the impact of the credit crunch and the deteriorating property market (Masterman, 2002). The reality for Armitt is that at that stage in the programme, there were fewer and fewer opportunities for cost saving and more and more opportunities for costs to rise. With construction activity on the vital venues and facilities starting and major infrastructure contracts let, the time for change was running out. For example, the saving from reorganizing venues for handball and basketball and moving fencing out of the park took nine months to plan and approve (Smith, 2003).

Coming up with similar high-value savings would be di-cult as there was less time available. That is not to say further changes would not be required to the 2012 plans, not least due to the so-called "Beijing factor." Lessons from the Games in Beijing could cause a rethink of designs or operations even at this late stage (Masterman, 2002). Armitt's role would be to ensure that any changes that are proposed at that stage were made with a full understanding of the consequences (Turner, 2005).

For people who would not understand construction Armitt tried to bring a greater understanding of the construction process and the risks and the capacity of the industry. He tried to give people con-dence in the industry to deliver. In the immediate term the biggest challenge was building things on time and to budget -- that was what they were there to do. Controlling costs in the current global economic situation would not be easy (Masterman, 2002).

The Olympic Stadium is a major work projected to take place in view of the 2012 London Olympics. The Stadium will have 80,000 seats and will host, amongst others, the opening and ending ceremonies, as well as the main athletics events. The focus of attraction for several million Olympic watchers, it has been identified as a "flagship venue" by the London Olympic organiser. The new construction will be part of the wider Olympic Park, which includes several buildings and venues (Smith, 2003).

The Client of the Olympic Park is the Olympics Delivery Authority (ODA). From an analysis of its senior management team, it appears to be a knowledgeable Client with a lot of experience in projects. However, taking into account the uniqueness of the project, its large size and major public impact, this analysis considers that the Client needs enhanced support in delivering a successful project (Masterman, 2002). It is thus recommended that the Client employs a project management consultant (Programme Manager), which would support the projects' delivery (Turner, 2005).

The Olympic Park is treated as a programme of projects. The advantages of working with a programme rather than individual projects are comprised by efficiency and effectiveness goals (effective resource utilisation, knowledge transfer, management of the project interfaces, improved coordination) and business focus goals (alignment of projects to the wider culture, values, requirements and drivers of the organisation) (Smith, 2003). Thus, managing through programmes should, at least theoretically, produce coherency and better coordination of the projects. In practice, there are several challenges of delivering a project that is part of a programme (Turner, 2005). Graham and Male mention a project's rank as being vital to its success, as a prioritised…

Sources used in this document:
References

1. Smith, N.J. Engineering Project Management. 2nd edition, Oxford, Blackwell Science, 2003, pp. 237.

2. Turner, J.R. The Commercial Project Manager. London, McGraw Hill, 2005, pp. 259.

3. Masterman, J.W.E. Introduction to Building Procurement Systems. 2nd edition, London, Spon Press, 2002, pp. 61.

4. Turner, J.R. The Commercial Project Manager. London, McGraw Hill, 2005, pp. 259.
Cite this Document:
Copy Bibliography Citation

Related Documents

London 2012 Olympic Cultural Impact
Words: 2900 Length: 10 Document Type: Essay

NA). Sebastian Coe, the "star" of the emotive video in London's bid to host the 2012 Olympics, reflects on the fact that watching the Olympics as a child at home in Sheffield, inspired him. Speaking at the Sport Accord conference in Beijing, Coe emphasised the need to use online communities and new media to stimulate young people's interest in sport and activity. He stressed the need to involve youth to

Olympic Games of Ancient Greece
Words: 1779 Length: 5 Document Type: Term Paper

Olympic Games of Ancient Greece The legends surrounding the beginning of the Olympic games are many, but it is generally believed that Heracles, the son of Zeus, founded the ancient Greek Olympic games. There is some evidence that the games had been going on for longer than we have written records for. The first records of the games at Olympia are from 776 BC. The first Olympic games were not the

London 2012 Olympic Games How Do the
Words: 2120 Length: 7 Document Type: Book Report

London 2012 Olympic Games How do the Closing Ceremonies in the Beijing 2008, the Athens 2004, and the Atlanta 1996 rate? Beijing 2008. A viewer would be hard pressed not to like the Beijing Closing Ceremony, especially if they were a fan of fireworks. When the Olympic athletes wave goodbyes to the audience, it is always jubilant and often free-form -- a favorite was two middle-easterners in their formal white robes standing

London Olympics Williams Needs to Optimize on
Words: 384 Length: 1 Document Type: Essay

London Olympics Williams needs to optimize on a number of different dimensions. The Olympic Committee wants to maximize total ticket sales, but also needs the revenue that is generated. However, the Committee also has motives for ensuring that tickets are affordable for locals, and that fans of the various sports can get tickets to events should they so desire. There are other sources of revenue, but the public relations dimensions of

Marketing Strategies of the London 2012 Olympic Games
Words: 1893 Length: 7 Document Type: Essay

Marketing Strategies London 2012 Olympic Games Similar to the rest of the world, the United Kingdom has been faced with the devastating effects of the internationalized economic crisis. But as the crisis continues to unfold, the country moves on to address its other issues as well. One of these issues is represented by the fact that the country's capital would represent the host of the 2012 Olympic Games. The preparations for organizing

ABC London Events Co
Words: 3106 Length: 11 Document Type: Essay

Operations Management Licenses and Requirements Event Management Risk Management CSR and Sustainability ABC London Events Co. will have many considerations to make before deciding on whether to host an event. One of the initial decisions will undoubtedly be financial as for-profit event management companies must return an adequate return to their investors. However, once the business case for the event is made, this is only the beginning and there are many subsequent decisions to

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now