Construction of London Olympic Stadium
Within the management-orientated system, the solution proposed is Construction Management (CM). Under the CM system, the Client employs an Architect and a Construction Manager, who oversees the works of individual Contractors (Smith, 2003). The system ensures that the Contractor and the Architect are put on an equal footing before the Client, and that the Construction Manager is able to provide design advice, particularly in regards to buildability. Compared to the Management Contracting (MC) system, the Client still enters in a contractual relationship with the Contractors (Masterman, 2002). This relieves some of the risk from the Construction Manager, and also allows the Client to better control the hiring process and the performance of the Contractors. This may be a key element in ensuring the timely and quality delivery of the Stadium project (Turner, 2005).
The organizational structure proposed is summed up below:
-level management
Project-level management
* Programme Manager does not have contractual links with other parties except for the Client.
Client
Manager
Architect (Concept Design)
Construction Manager
Contractor 1
Contractor 2
Contractor 3
Architect (Stadium Design)
The CM system can achieve the key objectives of Time and Quality in this project (Smith, 2003). Thus, CM has been associated with a 'prestige' level of quality, according to the Construction Round Table's guide to the building process, cited in Masterman. In addition, Masterman points out that research shows that on average, design and construction are completed more quickly than using conventional systems (Turner, 2005). The Cost of the project may be mitigated by increased competition and control over costs achieved if the employer enters direct contracts with contractors. Other advantages include a better working relationship within the project team and more constructive attitudes at managerial and operational levels (Masterman, 2002).
In regards to the payment mechanism, the project is complex and high profile; therefore, risk should be shared to some degree between the Client and the Contractor. The solution suggested is the use of a cost-reimbursable system, more specifically target cost (Turner, 2005). Cost-reimbursable systems are open-book accounting, based on payment of actual cost incurred by the Contractor plus overheads and profit. Amongst the cost-reimbursable systems, target cost is the more suitable for this project, as it could give a provisional indication of the final cost (Smith, 2003).
In accordance with CIRIA Report R85, cost-reimbursable contracts should be used in case of:
1.Inadequate definition of the work at the time of tender due to emphasis on early completion and/or an expectation of substantial variation in work content
2. Work of exceptional organizational complexity i.e. multi-contract situation, involvement with statutory undertakers and/or when access is restricted
3. Work involving technical innovation or exceptional technical complexity
4. Any other situation involving major unquantifiable risks to the Contractor, including effect of inflation, work below ground level and/or abnormal industrial relations
5. Some recurrent work
The Architect for the in-depth design would generally be expected to work in parallel with the Construction Manager and some of the Contractors; the estimation of proper Bills of Quantity might be difficult at the beginning (Smith, 2003). The specific requirements of the Client, the problematic ground conditions, and issues related to the inflexibility of time and quality standards may cause substantial variation (defined by CIRIA R85 as more than 15-20% of the tender price). Organizational complexity is present through multiple contracts; access might also be a problem due to the ongoing works on several adjacent sites (Masterman, 2002). Technical innovation and technical complexity are also issues to consider, as the stadium's design must reach iconic level and allow for the later conversion into the 25,000 seat permanent stadium. CIRIA R85 also argues for the cost-reimbursable payment system when the Client has a particular interest in maintaining good labor relations, which is an important aspect...
NA). Sebastian Coe, the "star" of the emotive video in London's bid to host the 2012 Olympics, reflects on the fact that watching the Olympics as a child at home in Sheffield, inspired him. Speaking at the Sport Accord conference in Beijing, Coe emphasised the need to use online communities and new media to stimulate young people's interest in sport and activity. He stressed the need to involve youth to
Olympic Games of Ancient Greece The legends surrounding the beginning of the Olympic games are many, but it is generally believed that Heracles, the son of Zeus, founded the ancient Greek Olympic games. There is some evidence that the games had been going on for longer than we have written records for. The first records of the games at Olympia are from 776 BC. The first Olympic games were not the
London 2012 Olympic Games How do the Closing Ceremonies in the Beijing 2008, the Athens 2004, and the Atlanta 1996 rate? Beijing 2008. A viewer would be hard pressed not to like the Beijing Closing Ceremony, especially if they were a fan of fireworks. When the Olympic athletes wave goodbyes to the audience, it is always jubilant and often free-form -- a favorite was two middle-easterners in their formal white robes standing
London Olympics Williams needs to optimize on a number of different dimensions. The Olympic Committee wants to maximize total ticket sales, but also needs the revenue that is generated. However, the Committee also has motives for ensuring that tickets are affordable for locals, and that fans of the various sports can get tickets to events should they so desire. There are other sources of revenue, but the public relations dimensions of
Marketing Strategies London 2012 Olympic Games Similar to the rest of the world, the United Kingdom has been faced with the devastating effects of the internationalized economic crisis. But as the crisis continues to unfold, the country moves on to address its other issues as well. One of these issues is represented by the fact that the country's capital would represent the host of the 2012 Olympic Games. The preparations for organizing
Operations Management Licenses and Requirements Event Management Risk Management CSR and Sustainability ABC London Events Co. will have many considerations to make before deciding on whether to host an event. One of the initial decisions will undoubtedly be financial as for-profit event management companies must return an adequate return to their investors. However, once the business case for the event is made, this is only the beginning and there are many subsequent decisions to
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now