Verified Document

Contract And Pricing Integration Data Analysis Chapter

Production Case Study PRICE NEGOTIATION MEMORANDUM

(The prenegotiation objectives establish the Government's initial negotiation position. They provide parameters that will be used in the contracting officer's final determination of a fair and reasonable price. They should be based on the results of the acquisition team's analysis of the offeror's proposal, taking into consideration all pertinent information including field pricing assistance, audit reports and technical analysis, fact-finding results, independent Government cost estimates, and price histories. The contracting officer must establish and document prenegotiation objectives before the negotiation of any pricing action.

A PNM must be a stand alone document that will pass scrutiny in court. The reader should not have to refer to audits or technical reports to make sense of the PNM.)

TEAM:

TEAM MEMBERS: (List the first and last names and positions of each person representing the Government here.)

First and Last names

Position

Peter John

Senior Contracting Specialist

Allen Austin

Contracting Specialist

Jane Dickens

Assistant Contracting Specialist

Helen Anderson

Assistant Contracting Specialist

Johnson Holland

Assistant Contracting Specialist

Joe Rogers

Assistant Contracting Specialist

Acquisition Background:

(Include the purpose of the negotiation and a description of the acquisition.)

The purpose of the document is to present the Price Negotiation Memorandum for the acquisition of the H-19 Mission Computer as well as the Operational Flight Programs for the H-19A helicopter. Department of Defense intends to upgrade the H-19 Mission Computer as well as the Operational Flight Programs of the H-19A. The H-19A helicopter is designed to meet the Army troop carrier and ground support. Presently, the H-19 also supports the U.S. Marine, Navy, Air Force, the Department of Interior and Coast Guard. The U.S. government also uses the H-19 to support the peacekeeping. However, the H-19 requires a significant improvement in speed, range and load capabilities, and the MAS (Malahy Aero Systems) are the sole prime contractor to satisfy the G-19 acquisition. In essence, the MAS and the government have agreed to complete the contract within 19 months.

Negotiation Summary:

(Describe the quality of cost or pricing data and the extent it was used. Include a discussion of contract type and elements of price that should be considered, together with issues of risk and uncertainty to the contractor and the Government.)

The negotiation is between the government and the Malahy Aero Systems, which is the Contractor to upgrade the computer system of the government H-19A helicopter.

The contactor has submitted the costs of materials to complete the 19-month project. The contractor submitted the total costs of $43,868,081; however, the government objective was $37,659,750. Despite the variance recorded, the company was still able to record the 12% profits of $4,519,170

Summary:

(Provide the status of any contractor systems considered in this negotiation.)

The contractor's accounting systems and material management as well as internal controls for the material management are adequate; however, the control risk is still low. The contractor records employee labor both the direct and indirect labor. Additionally, we consider that both the labor accounting system as well as related internal controls as adequate and carrying low risks based on our assessment.

The pricing and cost data submitted by the company to support the materials are inadequate because their preparation is not in accordance with appropriate FAR provision, and applicable cost accounting standard. Moreover, the contractor has not delivered an adequate documentation to back up its position. The concept "question costs" are the costs that may not be allowable or allocated to the contract. On the other hand, the term "unsupported costs" in our opinion refer to the allocated and allowable, however, the documentation provided is insufficient to back up the dollar amount in the proposal.

Cost Analysis Summary:

The contractor uses the element such as the material, Material Overhead, Engineering Labor, Engineering Overhead, Manufacturing Labor, Manufacturing Overhead, Other Direct Costs, G&A and Cost of Money for the proposal pricing. However, there is still a variance between the contractor cost data and government objective. The total price proposed by the contractor is $49,110,651

; however, the government objective is $43,871,896 revealing the variance of $5,238,755

(Then, fill in the following table with the government objective price for each cost element.)

Element

Contractor

Proposed

Government

Objective

Reference

Material

$20,976,910

$19,565,594

Engineering Group 66-9210 = $158,990

67-1100 = $481,175

67-5200 = $593,409

68-2400 = $98,342

68-3800 = $47,883

68-4800 = $324,587

68-5300 = $193,758

69-1100 =$19,078,766

Total = $20,976,910

Material Overhead

$897,812

763,058

Material Overhead rate =4.28%

Based on the current company forecast

Engineering Labor

$7,018,980

$7,018,980

Yr 1: 35,900 hrs x $35.72 = $1,282,348

Yr2: 140,250 hrs x $35.72 = $5,009,730

Yr3: 20,350 hrs x $35.72 = $726,902

Total = $7,018,980

Engineering Overhead

$3,287,690

$2,912,877

Engineering Labor Overhead rate = 46.84%,

Based on the current company forecast

Manufacturing Labor

$230,676

$230,676

Yr 1: 400 hrs x $25.15 = $10,060

Yr 2: 1,787 hrs x $25.15 = $44,943

Yr 3: 6,985 hrs x $25.15 = $175,673

Total = $230,676

Manufacturing Overhead

$253,444

$251,898

Manufacturing Overhead rate = 109.87%

Based on the forward pricing rate agreement

Other Direct Costs

$5,822,798

$3,418,235

Engineering Reproduction = $89,483

The calculation is derived using the current accounting information available from the latest fiscal year and adjusted based on the estimated of current sale year forecast.
Cost of Money

180,000

180,000

Amount agreed upon in conjunction with government auditor

Total Cost

$43,868,081

5,264

Profit

5,242,570

$4,700,560

Based on the 12% of the forecasted Total cost

Total Price

$49,110,651

$43,871,896

Significant Considerations:

The DCAA (Defense Contract Audit Agency) has audited the proposal upon receipt of the proposal development of the "H-19 Helicopter mission computer enhancement." Based on our opinion, the pricing or cost data in the proposal are adequate for the negotiation purpose. However, we remark that the pricing and cost data that the offeror has submitted to support the materials are inadequate because the data are not prepared in accordance with the applicable "Cost Accounting Standards and appropriate provisions of FAR (Federal Acquisition Regulation) and DFARS (Defense Federal Acquisition Regulation)." CON 217 (nd). The report of this audit is qualified pending the time the DCAA receives the technical report.

(Discuss the most significant facts or considerations controlling the establishment of the prenegotiation objectives. To the extent, such direction has a significant effect on the action, a discussion and quantification of the impact of direction given by Congress, other agencies, and higher-level authorities.)

Element Discussion/Component Breakdown:

(Discuss each major element of cost and if necessary, sub-elements, as well as profit and price for the acquisition. Always begin with the amount the contractor has proposed and then the amount of the government objective. It may seem redundant to keep providing the amounts when the Summary shows them, but large acquisitions may require lengthy PNMs and readers should not have to flip back and forth to compare the amounts.)

1. Material: The contractor proposed total direct material costs of $20,976,910. This major element of cost has been divided into separate engineering groups; therefore, the cost analysis was done on each engineering group to determine the Government's total material cost objective. The last four digits refer to the work-numbering package for the project and they are in accordance with the normal acceptable practice. The auditors and the company agree substantially in the area.

Engineering Group

Contractor's Proposal

Questioned Costs

Unsupported Costs

66-9210

$158,990

$34,294

$23,980

67-1100

481,175

140,000

341,175

67-5300

593,409

0

0

68-2400

98,342

0

0

68-4800

566,228

47,883

0

69-1100

$19,078,766

823,984

0

Total

$20,976,910

$1,046,161

$365,155

(Discuss in DETAIL how you developed your objective. Who provided the information? What info was provided? What analysis techniques were used? Do this for each engineering group.)

Engineering Group 66-9210:

The contractor proposed $158,990 for this engineering group. The Government objective is $100,716. The Government objective position is based on the questioned costs of $34,294. Thus, we questioned the proposed costs of $34,294 because the company used the $158,990, which is the same amount for the 22-month schedule since the new project is 19-month schedule. Moreover, there are unsupported costs of $23,980 that the contractor proposed for the security equipment. In essence, the Malahy has agreed to remove this unsupported amount.

Engineering Group 67-1100:

The contractor proposed $481,175 for this engineering group. The government objective is $0. In essence, we question the $140,000, which is the proposed costs of the CLS (cartridge load software) since the cost is no longer needed based on the initiation on the proposal development meeting. Moreover, the remaining $341,175 is unsupported because the cost is the quote for the Orbit Science for the Fairchild defense, which has already expired. Malay's negotiator proposed 7% reduction, however, the negotiation has not taken place, thus, we cannot consider this amount as supported. Meanwhile, we have deleted the entire $481,175 proposed for the Engineering Group.

Engineering Group 67-5300:

Under this engineering group, we take no exception with regard to the material costs.

The contractor proposed $543,409 for this engineering group. The Government objective is also $543,409.

Engineering Group 68-2400:

The contractor proposed $98,342 for this engineering group. The Government objective is $98,342. Under this engineering group, we take no exception concerning the material costs.

Engineering Group 68-4800:

The contractor proposed $566,228 for this engineering group. The Government objective is $518,345. We question $47,883 as the vendor support cost because this task is no longer needed based on the contract requirements. The cost of the earlier upgrade 2 in the table below reveals that there was a temporary shortage of the IT (Information Technology) personnel and materials leading to the higher costs of $706,993 during that period. Thus, we do not feel that that the proposed costs support this contract.

Upgrade

Cost

Upgrade 1

$521,289

Upgrade 2

$706,993

Upgrade 3

$528,390

Upgrade 4

$508,300

Average

$566,228

In opinion, we should use the average costs of the last two upgrades which is ($528,390 +…

Sources used in this document:
Reference

CON 217 (nd). Cost Analysis and NEGOTIATION Technique

© Management Concepts Incorporated

1-1

1-4
Cite this Document:
Copy Bibliography Citation

Related Documents

Pricing Department and Strategic Profitability
Words: 851 Length: 3 Document Type: Essay

From a supply chain standpoint, pricing departments must also create a high level of communication and collaboration across a business as well. Their role is to be the orchestrators of internal effort to manage suppliers to pricing and margin levels, ensuring consistency and focus on share goals. This is one of the primary reasons pricing has now become a strategic initiative within many businesses. For change to occur in

Framework for Awarding Audit Contracts by US Government Departments...
Words: 15848 Length: 58 Document Type: Term Paper

awarding audit contracts by U.S. government departments and agencies Audit Management Red Rationale for and Objectives of the project main and secondary Desktop or literature search Rationale for Search Methodology LITERATURE/DESKTOP RESEARCH Authoritative sources Desktop Findings Justification for audits Evolving role of auditors Types of audit contracts Understanding the Audit Process Best practices and benchmarking Terminology Case Studies Audit management is a fundamental element in government accountability, control and performance management. Certainly there is justification within the Federal government to conduct audits of contracts for the

Pricing and Contract Integration: Procurement
Words: 4747 Length: 15 Document Type: Essay

Procurement: Pricing and Contract Integration Federal procurement contracting has over the last few years been a subject of increased public and congressional interest, particularly because of the growing concern that noncompetitive procurement practices may be on the rise in the assignment of government contracts. The rising number of cases and public reports implicating federal agencies in alleged misconduct involving non-competitive contracts has drawn the attention of both Congress and the Executive

Social Networking a Vertical Integration Strategy Is
Words: 966 Length: 3 Document Type: Essay

Social Networking A vertical integration strategy is when "a firm owns its upstream suppliers and downstream buyers" (QuickMBA, 2010). There are a number of different ways that this could manifest for a firm in the social networking business. The first is that one needs to consider who the upstream suppliers are, and who the downstream buyers are. The inputs in a social networking business are everything from servers and web development

Diesel Fuel Pricing Effects on
Words: 1897 Length: 6 Document Type: Research Paper

Threats: Loss of industry as prices of oil are unstable due to market fluctuation Long-term contracts cannot be formulated in the basis of changing prices Gradual increase in prices can result into economic turmoil as raw materials and finished product prices will be increased lowering the economic process Conclusion: The trucking enterprises are significant in creating the United States transportation and freight industry. The transportation of raw materials and finished goods in required as most

The Advantages and Disadvantages of Price Based Contracting Methods...
Words: 2569 Length: 9 Document Type: Term Paper

Comparing the Advantages and Disadvantages of Cost-Based and Price-based DoD Contracting MethodsFor several years, the Department of Defence has primarily relied on cost-based proposals for most of its contracting processes. This emphasis has dramatically influenced the imposition of specific accounting systems, lost focus on the best value, and extensive auditing. Commercial markets are increasingly driving the rate of change and adoption of technology.Hence, the intensity of investment in and the

Sign Up for Unlimited Study Help

Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.

Get Started Now